Telegraph Road Construction Information

9/28/23: Telegraph Road Construction Updates

Work Completed Week of September 25:

  • Builders installed the 6” Aggregate Shoulder along Telegraph Road, from Route 22 to Wilmot Road. Also, installed Aggregate Wedge Shoulder along Telegraph Road, from Wilmot Road to North Avenue.
  • Another Builders crew completed Paving 2” HMA Surface for the remaining driveways.
  • F. Espinoza continued landscape restoration, seeding, and installing erosion control blanket. (The weather has impacted the landscapers production this week)

Issues Encountered:

  • No issues encountered.

Anticipated Schedule for Week of October 2:

  • Builders will perform HMA Patching on the new Bike Path. These patches will remove damaged asphalt and trip hazards where the new path and sidewalk meet.
  • F. Espinoza will perform landscape restoration, placing 4” topsoil, seeding, and installing erosion control blanket. Also, they will reinstall brick pavers located at 2140 Telegraph Road.
  • D2K is tentatively scheduled to perform pavement striping following the landscape restoration.

Neighborhood Impacts:

  • Residents should expect slight delays on Telegraph Road, but each contractor will have flaggers to help traffic drive through the work zone safely.

Please contact Village Manager Stephanie Hannon at shannon@villageofbannockburn.org or at 847-405-3022 with any questions or concerns.