The Village of Bannockburn is excited to extend the life of our streets by undergoing a comprehensive street improvement program. Construction is scheduled to begin September 22, 2025 and conclude by late November 2025, weather permitting. Download the construction flyer for more information, and view the construction notes below for weekly updates. Be sure to subscribe to the Bannockburn Byline for regular construction updates and other Village-related news.
Please direct any questions or concerns related to this project to Resident Engineer Chris Allen of Baxter & Woodman Consulting Engineers at callen@baxterwoodman.com or 815-444-3233.

LRS Service Alert for All Residents:
- To accommodate milling and resurfacing operations, LRS will begin servicing residential routes at 6.a.m. until the road project is completed. Notice will be provided once regular service hours resume.
- This will impact garbage/recycling collections on Mondays and yard waste collections on Wednesdays.
10/17/2025: 2025 Street Improvement Updates
Work Completed Week of October 13:
- A new 2” layer of asphalt surface was paved on all the roads. Half of Meadow Lane, Sunset Lane and Bannockburn Court will be finished today, 10/13.
- Driveways that were impacted by the curb and gutter or paving work were restored.
- Started to prepare for landscape restoration.
Anticipated Schedule for Week of October 20:
- Finish landscape restoration.
- Place shoulder gravel where needed.
- Restripe pavement markings.
- Cleanup and complete punch list items.
Neighborhood Impacts:
- No major neighborhood impacts are expected. Thank you for your patience and cooperation during these important roadway improvements!

10/10/2025: 2025 Street Improvement Updates
Work Completed Week of October 6:
- The contractor replaced several storm sewer structures on Meadow Lane and Aitken Drive and finished the curb and gutter.
- The old asphalt was milled to remove the top 2”.
- The asphalt base was patched with new asphalt, as needed.
- Began driveway restorations at curb and gutter repair sites.
Anticipated Schedule for Week of October 13:
- The contractor will pave a new 2” layer of asphalt. One lane will be paved at a time as crews progress through each street. Where the road is wide enough for 2 cars to pass, vehicles will be able to drive around the operation. On Valley Road and Aitken Road where it is much narrower, vehicles will have to enter from one end or the other depending on where the operation is.
- The work will progress from north to south in the following order (on these estimated days of the week):
- Broadley’s Court (Monday)
- Dunsinane Lane (Monday)
- Aberdeen Court (Tuesday)
- High Terrace Lane (Tuesday)
- Stirling Road (Wednesday)
- Valley Road (Wednesday)
- Bannockburn Court (Thursday)
- Robin Road (Thursday)
- Meadow Lane (Thursday/Friday)
- Orchard Court (Friday)
- Aitken Drive (Friday)
- Sunset Lane (Friday)
Neighborhood Impacts:
- From Monday, October 13 through Friday, October 17, please do not park vehicles on the street while paving operations are taking place.
10/03/2025: 2025 Street Improvement Updates
Road Closure Notice to Residents Along Meadow Lane:
With Village approval, a portion of Meadow Lane will be temporarily closed from 8:30 a.m. to 5:30 p.m. on Monday, October 6th through Wednesday, October 8th. The street will be briefly re-opened between 3:30-4:00 each day to allow school busses to pass through.
The closure will affect only the area directly in front of 1915 Meadow Lane, where crews will be excavating beneath the street to connect the water service for a new home currently under construction. This work will not impact the road resurfacing project timeline.
You will still be able to travel in other directions on Meadow Lane, but through traffic past 1915 Meadow will not be possible during working hours. The road surface will be covered overnight and will be passable.
The general contractor for this project will hand deliver letters to all affected residents. Should you have any questions or concerns, contact Public Works & Building Dept. Manager Sam Barghi at 847-945-6080 or sbarghi@villageofbannockburn.org.
Work Completed Week of September 29:
- The contractor removed sections of curb and gutter and replaced with new concrete.
- Storm sewer structures in the curb line were adjusted as needed to improve drainage.
- There are several locations remaining on Meadow Lane and Aitken Drive where storm sewer structures will be replaced and then the curb and gutter will be finished.
Anticipated Schedule for Week of October 6:
- The contractor will be milling the old asphalt to remove the top 2”. The operation will progress down each street milling one side of the road at a time. Where the road is wide enough for two cars to pass, vehicles will be able to drive around the operation. On Valley Road and Aitken Road where it is much narrower, vehicles will have to enter from one end or the other depending where operations are being performed.
- The work will progress from north to south in the following order (on these estimated days of the week):
- Broadley’s Court (Monday)
- Dunsinane Lane (Monday)
- Aberdeen Court (Tuesday)
- High Terrace Lane (Tuesday)
- Stirling Road (Wednesday)
- Valley Road (Wednesday)
- Bannockburn Court (Thursday)
- Robin Road (Thursday)
- Meadow Lane (Thursday/Friday)
- Orchard Court (Friday)
- Aitken Drive (Friday)
- Sunset Lane (Friday)
- After the top 2” of asphalt is removed, the remaining asphalt base will be patched as needed starting Wednesday October 8th prior to paving a new 2” layer of asphalt starting the week of October 13th.
- The contractor will also finish replacing several storm sewer structures where the curb and gutter is still removed.
Neighborhood Impacts:
- If curb and gutter was replaced at your driveway and you were required to park on the street, you can resume using your driveway on Friday, October 3.
- From Monday, October 6 through Friday, October 10, please do not park vehicles on the street while the milling operation is taking place.
09/26/2025: 2025 Street Improvement Updates
Work Completed Week of September 22:
- Setup traffic control in preparation for the work starting.
- Installed inlet filters in storm sewer structures to catch construction debris.
- Started saw cutting curb & gutter (expected this Friday, 9/26)
Anticipated Schedule for Week of September 29:
- The contractor will remove sections of curb & gutter and replace with new concrete. The locations identified to be replaced are due to deterioration and/or to improve drainage. The storm sewer structures in the curb line will also be adjusted, if needed.
- The work will progress from north to south in the following order:
1. Broadley’s Court (cul-de-sac)
2. Aberdeen Court
3. Stirling Road
4. Valley Road
5. Meadow Lane
6. Robin Road
7. Aitken Drive - NOTE: If your street is not included in the above list, curb and gutter work will not be required.
Neighborhood Impacts:
- If curb & gutter is being replaced at your driveway where access will be impacted, you will receive notice from the Resident Engineer on Friday, September 26 of when the work will occur during the week of September 2.
- If you have any private underground utilities (irrigation systems, lighting, pet fences etc.) in close proximity to the back of curb by the roadway, we ask residents to please mark them out with paint and/or flags to help prevent damage during construction. Public utilities within the Village Right-of-Way will be marked out by JULIE. Please contact the Resident Engineer to discuss any concerns related to this matter.